I looked at three aspects of the project plans:

 

Project Data

Presentation

Effort Estimation

Risk Management

Grade

2000261

Project: Assembly

End date:10.28

# Tasks:33

5

Charts: Pert

Writeup: brief, good organization

5

Person-weeks: 24

Method(s):UCP

& Bottom-up

4

Risk management plan

Schedule not risk-driven

A

2000308

Project: Tourn

End date:10.9

# Tasks:40

4

Charts:Pert

Writeup:

Could be better organized

5

Person-weeks:37 & 54

Method(s):UCP &

Bottom-up

5

General risk plan

Staged delivery

Client signoff

Risk-driven

Frequent testing

A

2000487

Project: Assembly

End date:9.15

# Tasks:19

5

Charts:Pert

Writeup:ok

5

Person-weeks:36

Method(s):UCP

3

Per task risk

No risk plan

Client signoff

Missed technical risk

A

2004534

Project: Assembly

End date:8.18

# Tasks:30

5

Charts:Gantt

Writeup:

Good task description

5

Person-weeks: 30, 24 & 27

Method(s): UCP,

Simple function point &

Bottom-up

5

Per task risk

Risk plan

Staged delivery

Risk-driven

A

2005220

Project: Assembly

End date:11.?

# Tasks:8

3

Charts: Gantt & Pert

Writeup:

Poor organization

(can't tell when project ends)

5

Person-weeks:20 (20 hours per week)

Method(s):UCP

4

Per task risk

Slightly risk-driven

Client signoff

A-

2005801

Project: Movie

End date:7.6

# Tasks:19

3

Charts:Gantt

Writeup:

hard to see total effort

3

Person-weeks:?

Method(s):bottom-up

Fairly informal justification

2

Per task risk

No plan for the risk

No client signoff

Not risk-driven schedule ("order decided up the dependencies")

B

2006083

Project: Tourn

End date:6.15

# Tasks:13

5

Charts:Pert

Writeup:ok

4

Person-weeks: 12.5 & 18

Method(s): UCP & cocomo

3

Per task risk

Staged delivery

No risk plan

A-

2007345

Project: Assembly

End date:7.10

# Tasks:22

4

Charts: Gantt

Writeup: brief

5

Person-weeks:23.7

Method(s):UCP

5

General risk plan

1 client signoff

Early sensor test

A

2010810

Project: Assembly

End date:7.17

# Tasks:16

4

Charts:Gantt

Writeup:

Reasonable task detail

Poor organization

5

Person-weeks:18

Method(s):UCP

5

General risk plan

Risk-driven

A

2012279

Project: Assembly

End date:9.5

# Tasks:8

4

Charts:Pert

Writeup:

merge user case with task

3

Person-weeks: ?

Method(s): UCP

(effort & scheduling is hard to follow, it's hard to compute total person weeks.)

5

Per task risks

Risk plan

A-

2013588

Project: Assembly

End date:6.25

# Tasks:10

3

Charts: Pert

Writeup:

Not well organized

(Pert chart all tasks one day)

5

Person-weeks:61

Method(s): UCP

3

Per task risk plans

Risk plans more fix than mitigate/avoid, not always useful ("redo" "keep reqs on hand")

Schedule not risk-driven, except for "checkpoints," no explicit test tasks, no client sign-off

B+

2014192

Project: Tourn

End date:7.30

# Tasks:12

5

Charts:Pert

Writeup: ok task detail

3

Person-weeks:25 (double from meeting)

Method(s): UCP

1

Schedule not risk-driven

No plan

(no any risk)

B

2014535

Project: Tourn

End date: 7.29

# Tasks:10

5

Charts: Pert

Writeup: detailed task

5

Person-weeks:17

Method(s): UCP

3

Per task risk

No plan

No general risk plan

No client signoff points

A

2014675

Project: Movie

End date:8.18

# Tasks:12

4

Charts:Pert

Writeup:

Brief task description

5

Person-weeks:33.3

Method(s):UCP

5

General risk plan

Staged delivery

Client signoff

A

2035472

Project: Movie

End date: 12.20

# Tasks:40

5

Charts:Gantt

Writeup:clear description

5

Person-weeks:62 & 115

Method(s): UCP &

Bottom-up

4

Staged delivery

Client signoff

No serious risk plan

A

2039611

Project: Movie

End date:7.10

# Tasks:28

5

Charts:Pert

Writeup:ok

5

Person-weeks:38

Method(s):UCP

5

General risk plan

Risk-driven

A

2043678

Project: Tourn

End date:6.16

# Tasks:32

5

Charts: Pert (1 hour task!)

Writeup:ok

4

Person-weeks:59 & 10.15

Method(s):UCP & bottom-up

(confused about total effort and project deviation)

4

Per task risk

No risk plan

Staged delivery

Client signoff

A

2045543

Project: Movie

End date:8.7

# Tasks:19

4

Charts:Pert & Gantt

Writeup:

Brief task detail

5

Person-weeks:29

Method(s): UCP

3

General risk list

No risk plan

No client signoff

A-

2045546

Project: Movie

End date:9.3

# Tasks:24

5

Charts:Gantt & Pert

Writeup:detailed task

5

Person-weeks:43

Method(s):UCP

5

General risk plan

Risk mitigation plan

Staged delivery

A

2046076

Project: Assembly

End date:9.24

# Tasks:10

1

Charts:Pert

Writeup:

Generic plan (install, new task, …), few links to Assembly Line Project,

"player?

'2

Person-weeks:14.5

Method(s): UCP

Shallow: just says there are 11 simple use cases, some confused or just wrong technical factor comments, e.g., significant training needed

3

Per task risk with plans

Schedule not risk-driven

Many risks operational, not development ("operator may run into problem", manager not available"), weak fixes ("test not run properly – have more tests")

C

2073762

Project: Tourn

End date:6.20

# Tasks:15

4

Charts:Pert

Writeup:

Kind of brief

4

Person-weeks:7

Method(s):UCP

(converted to hours incorrectly)

4

Per task risk

Risk plan

No technical risks noted

3 client signoff

A-

2076315

Project: Movie

End date:7.13

# Tasks:17

5

Charts:Gantt

Writeup:detailed task

Clear task charts

5

Person-weeks:38

Method(s):UCP

5

Per task risk

Risk mitigation plan

Staged delivery

Client signoff points

A

2077043

Project: Tourn

End date:9.1

# Tasks:24

4

Charts: Gantt

Writeup: detailed task

Task too brief

5

Person-weeks:11

Method(s):UCP

3

No plan

Per task risk

Client signoff points

No other risk plan

Staged delivery

A-

2080786

Project: Tourn

End date:6.18

# Tasks:13

5

Charts:Pert

Writeup: clear writeup

5

Person-weeks:22.7

Method(s): UCP

4

Per task risk

Risk plan

Schedule is Schedule not risk-driven

A

2086940

Project: Tourn

End date:8.6

# Tasks:28

5

Charts: Pert

Writeup: detailed task

5

Person-weeks:32

Method(s):UCP

3

Plan

Client signoff points

No specific risk

Staged delivery

A

2233172

Project: Movie

End date:10.3

# Tasks:17

4

Charts:Pert

Writeup: brief task

5

Person-weeks:54

Method(s):UCP

2

Per task risk

Schedule not risk-driven

No risk plan

B+

2254204

Project: Movie

End date:9.5

# Tasks:14

3

Charts:Pert (timing unclear)

Writeup: task descriptions OK but exact scheduling is left unresolved

2

Person-weeks: ?

Method(s):bottom-up seat-of-the-pants per-task estimates, no baseline, no total

3

Per task risk

No plan

B

2257983

Project: Tourn

End date:7.8

# Tasks:15

5

Charts: Pert

Writeup:

Brief task description

5

Person-weeks: 32.2 & 20

Method(s):UCP &

Bottom-up

5

General risk plan

Missed technical risk

Staged delivery

A

2264591

Project: Assembly

End date:8.3

# Tasks:11

3

Charts: Pert

Writeup:

hard to find things

need to label

poorly organized

4

Person-weeks: 28 (20 hours per week)

Method(s):UCP

3

Staged delivery

Per task risk

Risk-driven

No general risk plan

No technical risk

B+

2265290

Project: Movie

End date:7.18

# Tasks:15

5

Charts:Gantt

Writeup:ok

5

Person-weeks:31

Method(s):UCP

4

Per task risk

Risk plan

Schedule not risk-driven

A

2290601

Project: Movie

End date:9.11

# Tasks:26

4

Charts: Pert

Writeup:

Not clearly organized

5

Person-weeks:18

Method(s): UCP

5

Per task risk

Client signoff

Risk plan

A


Comments? Send mail to Chris Riesbeck.